1. Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% work had been completed. How many additional workers would be need to finish the task in scheduled time?

  • A. 50
  • B. 50
  • C. 50
  • D. 50

Answer: Option A