1. Mr. Jamal employed 50 workers to finish a work within 30 days. After 20 days he found out that only 50% work had been completed. How many additional workers would be need to finish the task in scheduled time?
- A. 50
- B. 50
- C. 50
- D. 50
Answer: Option A